How to plan multiple asset visits using a single vessel
1. Overview
The Shoreline Planning Board allows users to plan multiple asset visits using the same vessel, manage the associated personnel and activities, and download the planned transfer information in Excel format.
This functionality is particularly useful when a Crew Transfer Vessel (CTV) is scheduled to visit several wind turbines or other offshore assets during the same working day.
The following procedure explains the workflow demonstrated during our meeting on 25 November 2026.
2. Prerequisites
Before creating the transfer plan, ensure that:
- The relevant site and assets are registered in Shoreline.
- The vessel is registered and available for selection.
- Teams and personnel are registered.
- The required activity categories are configured.
- Your user account has the necessary planning, dispatch and export permissions.
3. Open the Planning Board
- Log in to the Shoreline Platform.
- Navigate to Planning Board.
- Open the timeline in the Team view.
- Select the required planning date using the date selector.
- Select Day as the timeline period to display the daily schedule.
For the OKAOGE account, confirm that the displayed time zone is Japan Standard Time (JST).
4. Create the first asset visit
- Locate the relevant team on the Planning Board.
- Double-click an empty area on the team's timeline at the intended activity start time.
- In the activity window, enter the following information:
| Section | Information to enter |
|---|---|
| Info | Activity category and planned start and end times |
| Connections | Relevant site and destination asset |
| Manpower | Assigned team and personnel |
| Transport – Drop off transport | Vessel responsible for transferring personnel to the asset |
| Transport – Pick up transport | Vessel responsible for collecting personnel from the asset |
| Remarks | Additional operational information, if required |
- Review the entered information.
- Click Save.
The planned activity will appear on the team's timeline.
5. Plan additional asset visits using the same vessel
Repeat the previous procedure for each additional asset that the vessel is scheduled to visit.
For each activity:
- Select the corresponding destination asset.
- Enter the planned start and end times.
- Assign the relevant team and personnel.
- Select the same vessel under Drop off transport.
- Select the appropriate vessel under Pick up transport.
There is no need to register a separate vessel for each asset visit.
Example: One vessel visiting three assets
The following example illustrates a CTV visiting three different assets during the same day.
| Visit | Asset | Start | End | Drop-off transport |
|---|---|---|---|---|
| 1 | 001 | 08:00 | 09:00 | CTV 1 |
| 2 | 002 | 09:30 | 11:00 | CTV 1 |
| 3 | 005 | 11:30 | 13:00 | CTV 1 |
The above times are illustrative. Actual timings, personnel assignments and pickup arrangements should reflect the intended operation.
Additional activities can also be created for other vessels during the same day.
6. Review and manage the transfer plan
Once all activities have been created, review the schedule on the Planning Board.
To focus on a particular vessel:
- Open the Planning Board filter panel.
- Locate the Transport filter.
- Select the vessel you wish to review.
Check the following before finalising the plan:
- Correct assets and visit sequence.
- Correct vessel assignments.
- Correct teams and personnel.
- Planned start and end times.
- Sufficient time for transfers between assets.
- Appropriate pickup arrangements.
- Potential scheduling conflicts and relevant warnings.
To modify an activity that has not been dispatched, double-click the activity, update the required information and save the changes.
Editable activities can also be repositioned on the timeline to adjust their scheduled times.
7. Dispatch the activities
The activities must be dispatched before they can be included in the Planning Board's transfer manifest export.
- Review the activities in the live Planning Board.
- Click the dispatch icon on each relevant activity.
- Address any applicable validation warnings.
- Confirm that all activities intended for the transfer plan have been dispatched.
If a dispatched activity needs to be rescheduled, use its undo-dispatch icon, make the necessary changes, save the activity and dispatch it again.
8. Download the transfer plan
After dispatching the relevant activities:
- Locate the Manifest button below the Planning Board timeline.
- Click Manifest.
- The Transfer manifest window will open.
- Select the date for which you want to download the transfer information.
- Under Select drop off transport, select the required vessel or vessels.
- Click Download.
- Once the export has been generated, open the downloaded Excel file.
You may select a single vessel to download its transfer information or select multiple vessels to include them in the same Excel workbook.
9. Understand the exported Excel file
When multiple vessels with dispatched activities are selected, the generated Excel workbook contains a separate worksheet for each vessel.
For example:
- Worksheet 1 – CTV 1
- Worksheet 2 – CTV 2
Each worksheet contains the relevant personnel and their associated planned activities.
The available information includes:
- Work date
- Transport name
- Seat number
- Team
- Personnel name
- Departure location
- Departure transport
- Shift start time
- Assets to be visited
- Planned transfer time
- Estimated pickup time
- Pickup transport
- Activity category
- Associated work order, where applicable
Where a person is assigned to multiple activities using the same drop-off vessel, their planned visits are represented in successive activity column groups.
Scroll horizontally within the worksheet to review the additional asset visits and their associated information.
10. Updating an existing transfer plan
If operational requirements change after downloading the transfer plan:
- Return to the Planning Board.
- Locate the relevant activity.
- Undo dispatch if necessary.
- Update the timing, asset, personnel or transport information.
- Save and dispatch the updated activity.
- Generate a new export using the required date and vessel selection.
Always ensure that the latest version of the transfer plan is communicated to the relevant Marine Coordination Centre (MCC) personnel, suppliers and vessel operators.
11. Troubleshooting
An activity is missing from the exported file
Check that the activity has been dispatched, the correct export date has been selected, the drop-off vessel matches the selected vessel, and the required personnel are assigned.
The vessel is not available for selection
Confirm that the vessel is registered in Shoreline and available to your account.
The Manifest button or Download option is unavailable
Confirm that you are online and that your user account has the required permissions.
An activity cannot be moved on the Planning Board
Check whether the activity has already been dispatched, completed or locked.
12. Important note regarding the Crew Manifest
Although the Planning Board download is labelled Manifest in Shoreline, the workflow described in this procedure covers the planning and export of vessel transfers across multiple assets.
The additional OKAOGE-specific Crew Manifest parameters are being addressed separately. The current export should therefore not be considered a complete replacement for the agreed Crew Manifest requirements until the remaining parameters have been aligned.
The multi-asset transfer planning workflow can be used independently of this outstanding requirement.