Personnel
Personnel
When adding personnel groups to a case, you can configure a variety of parameters — including whether the personnel are full-time or subcontracted, how many personnel are in the group, and what skills they have.
A personnel group defines a set of workers — including their type, availability, skills, and cost — that can be assigned to tasks in a case. This page covers all parameters available on personnel groups in Design Construction and Design O&M.
Personnel parameters
| Parameter | Description |
|---|---|
| Group type | Whether personnel are full-time employees or subcontractors. If you select Subcontractors, the Unlimited parameter becomes available.If you select Full time employees, the Availability parameter becomes available.See the Subcontractors and personnel utilization section for a note on the personnel utilization output when using subcontractors. |
| Unlimited | Whether the number of available personnel within the group is fixed or unlimited. If you select Unlimited, the Members parameter is no longer available. |
| Members | The number of personnel within the group. |
| Home base | The location where daily operations begin. This can be a port, offshore base, or Service Operation Vessel (SOV). |
| Availability | Whether the personnel are available all year, seasonally (between fixed dates), or only on certain weekdays. |
| Season | Note: O&M only. Only available when you enable a campaign on the personnel page. Whether the personnel are available inside or outside of the campaign dates. |
| Work hours | Whether work hours are fixed or staggered. Fixed: All personnel start and finish work at the same time. Staggered: Define the start time of the first shift, the shift length, the interval between shift start times, and the number of shifts per day. Shoreline calculates a staggered shift schedule based on these inputs and the number of personnel in the group. |
| Skills | Select which skills the personnel group have. Required skills are set on WTG commissioning tasks (Design Construction) and scheduled and corrective maintenance tasks (Design O&M). |
| Allowed transport | The logistics types (for example, vessel or helicopter) that are permitted to transport this personnel group. |
| Hourly salary | For full-time personnel: The annual salary per person. The annual salary is converted into a daily salary by dividing by 365.25 (accounting for leap years). The daily salary cost is then accrued for every day a member of the group is available. For subcontractors: The hourly salary per person. |