Shoreline provides permission-based access controls that allow administrators to define what marine coordinators, suppliers and other users can perform within the platform.

There are three relevant functions:

  • Dispatch: Finalising planned activities on the Planning Board.
  • Activity locking: Protecting activities against further modification.
  • Permit to Work approval: A formal approval workflow with designated approvers and issuers.

These functions serve different purposes and have different permission requirements.


Configure permission policies

We recommend establishing separate permission types for Marine Coordinators and Suppliers before issuing supplier accounts.

Step 1 – Open the Permission Matrix

  1. Log in using an administrator account.
  2. Navigate to Company Settings.
  3. Open Permission Types.
  4. Review the existing permission types in the Permission Matrix.
  5. Create or configure separate permission types for:
    • Marine Coordinator
    • Supplier

Each column represents a permission type, and each row represents an individual permission.

Step 2 – Configure the permissions

The following configuration is recommended as a starting point.

Permission Marine Coordinator Supplier
Planning Board – Access Enabled Enabled if required
Planning Board – Read Enabled Enabled if required
Work Orders – Create As required As required for activity creation
Work Orders – Update Enabled Subject to operational agreement
Work Orders – Lock As required Disabled
Permits to Work – Access Enabled As required
Permits to Work – Read Enabled As required
Permits to Work – Create Enabled As required
Permits to Work – Update Enabled As required
Permits to Work – Manage Enabled Disabled
Permits to Work – Delete As required Disabled
Audit Log – Access Enabled Disabled
Company Settings – Update Administrators only Disabled

The remaining permissions, including personnel registration, should be configured according to the responsibilities agreed between OKAOGE and its suppliers.

The Update permission under Work Orders requires particular consideration because it also controls certain Planning Board activity operations, even when activities are not associated with work orders.

Step 3 – Assign permission types to users

  1. Open the relevant personnel or user record.
  2. Locate the user's permission setting.
  3. Assign the appropriate permission type.
  4. Save the changes.
  5. Confirm that each supplier and marine coordinator has been assigned the correct permission type.

Supplier accounts should not be assigned administrator privileges or permit approval permissions.


Dispatching activities on the Planning Board

Dispatching indicates that a planned activity has been finalised for execution.

Dispatch an individual activity

  1. Navigate to Planning Board.
  2. Open the team timeline and select the required date.
  3. Locate the activity to be finalised.
  4. Review its asset, personnel, transport and timing information.
  5. Click the dispatch icon on the activity.
  6. Address any applicable validation warnings.
  7. Confirm that the activity is displayed as dispatched.

Dispatch multiple activities

  1. Open the live Planning Board.
  2. Click Dispatch below the timeline.
  3. Select the relevant start and end dates.
  4. Select the dispatch operation.
  5. Confirm the action.
  6. Review the resulting activity statuses.

Dispatched activities cannot normally be repositioned directly on the timeline.

To reschedule a dispatched activity, undo its dispatch, make the required changes and dispatch it again.

Current permission limitation

Planning Board dispatch is not a separate formal marine permit approval workflow.

Currently, there is no dedicated Planning Board permission that independently restricts final activity dispatch to marine coordinators while allowing suppliers unrestricted activity editing.

Therefore, if suppliers require permission to create and modify their own planned activities, the Planning Board dispatch function alone should not be treated as an MCC-exclusive marine permit approval mechanism.


Locking and unlocking activities

Activity locking is used to protect activity information against further changes.

Lock an activity

  1. Locate the activity on the Planning Board.
  2. Double-click the activity to open its details.
  3. Select Lock activity, where available.
  4. In the confirmation window, select Yes, please lock.
  5. Save the activity.

Unlock an activity

  1. Open the locked activity.
  2. Select Activity locked.
  3. In the confirmation window, select Yes, please unlock.
  4. Make the required changes and save the activity.

Activity locking should not be considered a substitute for a formal approval workflow. It is a data protection function rather than a separately authorised marine permit decision.


Restricting formal permit approval to marine coordinators

If the dedicated Permits to Work module is used, formal permit approval can be restricted through the Permission Matrix.

Configuration

  1. Navigate to Company Settings → Permission Types.
  2. Locate the Permits to work section.
  3. Enable Manage for the Marine Coordinator permission type.
  4. Disable Manage for the Supplier permission type.
  5. Save the permission changes.
  6. Ensure only authorised marine coordinators are assigned to permission types with this permission enabled.

Assigning approval responsibilities

When creating or configuring a Permit to Work:

  1. Open the permit record.
  2. Complete the required permit information.
  3. Assign authorised users in the following fields:
    • Coordinator
    • Approver
    • Issuer
  4. Select the applicable safety rule, if required.
  5. Submit the permit for the appropriate approval stage.

The Coordinator performs the initial review, the Approver reviews the formal permit, and the Issuer authorises its release for execution.

Where required by the operational procedure, these approval and issuance roles should be assigned exclusively to authorised MCC personnel.

Suppliers without the Permits to work – Manage permission cannot perform formal permit approval or rejection.


Approval history and audit trail

Formal Permit to Work

The formal permit approval workflow records the identity of users who approve or reject approval requests.

To review the approval information:

  1. Open the relevant Permit to Work record.
  2. Locate the Comments section.
  3. Review the recorded approval and rejection information.

Approval comments generated through the normal platform workflow include the user's name, date and time, action and any additional comment provided.

Planning Board activities

Changes to Planning Board activities, including dispatch status changes, are recorded through the system's activity audit mechanism.

However, the Planning Board does not provide the same dedicated approval history as the formal Permit to Work workflow.

Administrators can access the general Audit Log under Company Settings if the appropriate permission is enabled.

The availability of activity-specific dispatch details directly within the customer-facing Audit Log requires further verification. Shoreline support can assist with investigating specific activity changes where necessary.


Recommended operating procedure for OKAOGE

Before supplier accounts are issued, we recommend agreeing on the following division of responsibilities:

Suppliers

  • Register and maintain authorised personnel information.
  • Enter and maintain planned transfer activities within their agreed responsibilities.
  • Submit the transfer plan for MCC review through the agreed operational procedure.
  • Do not independently authorise marine operations.

Marine Coordination Centre

  • Review submitted transfer plans.
  • Verify personnel, vessel, asset and timing information.
  • Perform the final operational approval.
  • Maintain oversight of approved plans and subsequent changes.

If OKAOGE requires a system-enforced marine permit approval process that suppliers cannot perform independently, the dedicated Permit to Work functionality should be evaluated for this purpose.

If approval must take place exclusively through the existing Planning Board activity workflow, an additional permission-control requirement remains to be addressed.


Verification before supplier onboarding

Before issuing supplier accounts, we recommend testing the agreed configuration using one Marine Coordinator test account and one Supplier test account.

The test should confirm that:

  • Suppliers can perform the required personnel registration.
  • Suppliers can enter and update the intended planning information.
  • Suppliers cannot formally approve permits.
  • Marine coordinators can perform the required approval actions.
  • Approval identities are correctly recorded.
  • Planning Board dispatch and undo-dispatch behaviour is understood.
  • The approved operational procedure prevents suppliers from independently authorising marine operations.

This verification should be completed before supplier onboarding begins in January 2027.


Related documentation