Summary: This article clarifies whether the Loadout and installation tasks percentage setting applies to jack-up operations.

Loadout and Installation Tasks Percentage Setting

  • The Loadout and installation tasks percentage setting is designed to affect the durations of loadout and installation tasks, as well as cable-laying and burial times.

Applicability to Jack-Up Operations

  • Jacking up operations are not explicitly included under the Loadout and installation tasks. Therefore, the percentage set for loadout and installation tasks does not apply directly to jacking up operations.
  • Instead, jacking up operations fall under the "Technical maintenance parameters marine operation tasks" setting, which impacts all non-loadout and installation tasks, including jack-up durations.

Conclusion

In summary, the Loadout and installation tasks percentage setting does not apply to jack-up operations. Instead, the duration of jacking up is influenced by the Technical maintenance parameters marine operation tasks setting.